LOY YANG POWER & LOY YANG MINE
Loy Yang A is Victoria’s largest power station, producing 30% of the state’s electricity.
Pro Draft provides drafting services, 3D modelling, measuring and technical assistance to Loy Yang Power and its contractors on major and minor projects.
2007-2016 Unit 2, 3 & 4 Major Outages – Drafting Services in support of:
- New high efficiency turbine cylinder installations
- Generator refurbishments and upgrades
- Boiler Gas Outlet Duct refurbishment
- Main firing burner duct replacements
- Auxiliary fuel burner upgrades & replacements
- Quality control checking of components prior to start of outage
- Return to Store audit of unused items on completion of outage
2012 Ladder Compliance Audit to AS 1657
- Identified 600 ladders for replacement, repair or removal
- Defined objectives, goals, actions and measures
- Created audit template and database
- Used reporting mechanisms to help prioritise works
- Worked to a project-plan to meet targets
Loy Yang Mine is the largest brown coal mine in Australia providing the fuel source for both Loy Yang A & B power stations. Pro Draft provides on-site electrical and mechanical drafting services, 3D Modelling, measuring and technical assistance to the Loy Yang Mine.
2016 Tripper Stacker 4 Major Outage – Drafting Services in support of:
- Detailed 3D modelling for internal layout of electrical switchgear & external envelop for the new switchroom. (Stacker)
- Detailed 3D modelling of the internal layout of the switchgear and new floor plates. (Tripper)
- New access walkways to switchrooms
- Installation of new Stacker switchroom (including Lube room and Resistor room) Including 25Tonne C-Frame Lifting beam.
2015 Dredger No 15 Major Outage – Electrical Switchrooms, Loading Unit & Digging Unit (HV & LV)
- Detailed 3D modelling for internal layout of electrical switchgear & external envelop for the new switchroom.
- New access walkways to switchrooms.
- Removal/Installation of existing switchroom.
Support Trestle
- Detailed model for solidworks analysis
New VSD Motors
- Adapt existing structure to accommodate new drives.
- Design guarding to AS standards for new drives.
2014 Dredger No 15 Electrical Switchroom Piping – New insulated chiller piping for VSD upgrade
- Ablution block plumbing
Cabling – extensive 3D modelling for cable runs on Digging Unit underframe
Fire & General Service Piping
- 3D modelling for portable PRV sled
2014 Dredger No 16 Bucketwheel weightometer installation
- Detailed 3D modelling of bucketwheel boom
- Calculate mass for machine stability
2011-2012 Dredger No.14 & 15
- D15 Bucket Wheel replacement – Modelled new and existing wheels & chutes
- Detailed drawings for Bucket Wheel lug repair
- Detailed drawings of welding jigs required to centralise lug inserts & stabilise welding process
- Created removal & installation drawings for digging-unit steering-screw
- Detailed drawing for civil works & structural modifications